Image provided by: University of Oregon Libraries; Eugene, OR
About Applegater. (Jacksonville, OR) 2008-current | View Entire Issue (Sept. 1, 2011)
Fall 2011 21 Applegater Update on the Applegate Dam Hydroelectric Project BY marGaret deLLa santina On September 13, Symbiotics LLC held an open house at the Ruch Library to explain plans for construction of the Applegate Dam Hydroelectric project. The library meeting room was packed with residents hoping to learn about the impact of this upcoming project. In case you were not able to attend that informational meeting, this article is intended to bring you up-to-date. First, a little background: In December 2009, the Federal Energy Regulatory Commission (FERC) approved Symbiotics’ proposal for a 10-megawatt hydroelectric retrofit project. (This license was granted nearly five years after Symbiotics submitted their proposal in 2004.) Both before and after the FERC approval, numerous residents voiced concern about the aesthetic, environmental, and safety issues posed by the addition of taller, high-voltage transmission lines. In September 2010, a “contested case hearing” was held by the Oregon Department of Justice at the Ruch Library. This hearing was attended by an overflow crowd of community members, many of whom raised their concerns and questions to the Oregon Water Resources Department, Symbiotics LLC and their lawyers, and the presiding Oregon Administrative Law Judge. Clearly surprised by the outpouring of community concern, Judge Han eventually closed the formal hearing, and continued in a town hall meeting format. Judge Han eventually issued a preliminary approval of the hydroelectric project that did not require burying the under way between Symbiotics, Charter lines. Nonetheless, in part as a result of that Communications and CenturyLink. At hearing, in December 2010 Symbiotics the September 13 meeting, residents were announced their intention to bury the asked to complete a survey gauging interest entire 15 miles of transmission lines, from in obtaining (or switching to) high-speed the dam to the substation on Highway Internet; this data is critical to supporting 238 near Cantrall-Buckley Park. (Existing our case. If you are interested in the power-delivery lines will not be affected.) possibility of high-speed Internet, and did Symbiotics requested from FERC a license not complete a survey at the September amendment granting approval to “bury 13 meeting, please contact Jack Berger at all 15 miles of the transmission lines from CenturyLink (Jack.Berger@CenturyLink. com) and/or Greg the powerhouse to Templer at Charter their terminus.” learly surprised by the Communications Eric Steimle outpouring of community (Greg.Templer@ o f S y m b i o t i c s concern, Judge han eventually chartercom.com). e x p l a i n e d t h i s closed the formal hearing… The open decision—which house on September adds about 14% to the approximately $18-million project— 13 was hosted by Larry Hobbs, project as a reflection of Symbiotics’ desire to superintendent at Symbiotics. He was be “a good neighbor to residents of the joined by three representatives from Mowat, the engineering firm contracted Applegate Valley.” Those of us who support the use of to do the construction. Mike Kuntz the existing dam to generate non-fossil-fuel from Jackson County Roads Department energy were delighted with Symbiotics’ was also on hand to answer questions. decision, and began to talk with Symbiotics Tim Callahan, the project engineer representatives about other ways the project from Mowat, provided the following might be mutually beneficial. For instance, information about the schedule and one possible benefit is the prospect of logistics of the project: • Construction of the transmission extending high-speed Internet all the way out Upper Applegate Road. Currently, line route is scheduled to begin in mid- residents who live beyond the nine-mile January 2012, and estimated to take about marker must rely on slow dial-up or eight months, concluding toward the end expensive satellite connections. Symbiotics of summer 2012. • Trench-digging will begin at the has offered the use of their open trenches to any Internet provider that would like Ruch substation, and move from there to extend service along the transmission along Hamilton Road, then Upper route, and discussions are currently Applegate Road to the dam. C • Crews will work from 7 am to 5 pm most workdays, and generally not on weekends or holidays. • The trench will be approximately two feet wide and four feet deep. Open trenches will be clearly marked with signs, fencing, and/or lighted barrels. • When digging is scheduled to cross a driveway, residents will be given one to two weeks advance notice of the date/time. Crews will attempt to complete work on driveways within a few hours. • In several spots, the trench must cross the road. When the road must be closed, Mowat will provide several weeks’ advance notice, and will perform the work during off-peak hours. • A signboard will be posted outside the Ruch Library once construction has begun, showing the progress of the project and the area that is currently under construction. This board will be updated regularly. In addition, maps showing the transmission-line burial route are on display at the Ruch Library. Although this project is bound to be disruptive to many residents, Symbiotics and Mowat both are hoping to maintain good community relations through this process. If you have questions or concerns as the project progresses, you can direct these to Larry Hobbs, Project Superintendent: larry.hobbs@symbioticsenergy.com. For general information and updates on the project, a binder is available at the Ruch Library labeled “Applegate Dam Project.” Stay informed! Margaret della Santina • 541-899-9950 Upper Applegate Bicycle Lanes BY PhiL doLLison Following in the footsteps of Symbiotics, with their plans to construct a power-generating facility at Applegate Lake and lay the transmission lines underground along Upper Applegate Road, the Applegate River Watch Group, Inc., hopes to construct approximately nine miles of bicycle/pedestrian lanes along Upper Applegate Road, from Ruch to the far side of Applegate Lake. This will connect to approximately nine existing miles of bicycle lanes already in place along Upper Applegate Road. The nine-mile addition will provide almost 18 miles of safe bicycle/pedestrian lanes stretching from Ruch almost to the California border. In order to keep construction costs down, we are hoping to hire a retired roads engineer to work with us, coordinating with Jackson County Roads Department, to engineer and design the first section of road-widening for construction of bicycle/pedestrian lanes. Symbiotics has offered to deliver excess crushed rock for use as shoulder (bike lane) base material at no charge and Jackson County has agreed to allow us to store the crushed rock on county land along Upper Applegate Road. As our bicycle-lane project is getting started, we are looking for donations and pledges to begin our first section from the two-mile marker on Upper Applegate Road to Little Applegate Bridge. At the same time, the U.S. Forest Service is looking for grant funding for the approximately 2.3 miles of roadway they control along Upper Applegate Road. To date, we have $1,100 in an account at Rogue Federal Credit Union (under the auspices of the Applegate River Watch Group), as well as $1,900 in pledges. In addition, 14 local residents have agreed to support us with their tax-deductible donations. By the time Symbiotics begins trenching from Ruch to the Applegate Dam along Hamilton Road (in January of 2012), we hope to have sufficient funding to begin engineering our first section: Seven-tenths of a mile between Hamilton Road and Little Applegate Bridge. Applegate River Watch Group, Inc. is a 501(c)3 nonprofit community organization and, as such, all donations are tax-deductible. If you would like to donate to this worthy cause, please send your donation (or monetary pledge) to Applegate River Watch Group, Inc., 6621 Upper Applegate Road, Jacksonville, OR 97530. Phil Dollison 541-899-9601 Applegate River Watch Group, Inc. “Back in Time” is on vacation and will return in the Winter edition of the Applegater. FOR MORE THAN DUNGAREES T-SHIRTS • SWEATSHIRTS • SHORTS JACKETS • VESTS • SHIRTS JEANS • COATS • LINED PANTS SOCKS • BELTS • HATS OVERALLS • RAINWEAR • GLOVES WOMEN’S CARHARTT INFANT AND CHILDRENS IN STOCK LOW EVERYDAY PRICES CUSTOM EMBROIDERY AVAILABLE HOURS: Friday 8 a.m. - 5:30 p.m. Saturday 8 a.m. - 12 p.m. 772-7538 1321 North Riverside • Visa Discover Mastercard American Express Medford Serving the valley in sales & service for 46 years, 1965-2011 Crater Chain Saw