Image provided by: Nyssa Public Library; Nyssa, OR
About The Gate city journal. (Nyssa, Or.) 1910-1937 | View Entire Issue (July 30, 1936)
TH E G ATE C IT Y JO U RNAL, TH U R SD AY, JU L Y 30,1936 Local Engineer Writes Interesting Article On The Construction Of The Big Malheur River Siphon The following article by Richard (Dick) Young of Nys- sa, appeared in the July num ber of The Reclamation Era, a magazine published in Washington D. C. In the article Mr. Young has made a clear description of the M al heur River siphon, and the methods used in constructing this big feature of the pro ject's iirigation system. MALHEUR RIVER SIPHON A view of the Mal- neur Siphon being laid. When com pleted it was nearly miles long and will Irrigate 17.000 Dead of the railroad crossing. The siphon can be drained through one 18-inch needle valve and one 12-inch gate valve installed at the river crossing and four 4- inch valves located at various points of the line. CONSTRUCTION The construction of the siphon was advertised under Specification No. 598, which provided for alter native proposals on precast concerte pipe to be buried under ground and on plate steel pipe to be supported M A L H E l'R R IV E R SIPHON above the surface as above describ By Richard A. Young, Assistant ed. The work under each alterna tive was divided into two schedules, Engineer one including roughly the construc The Malheur River Siphon is a tion of inlet and oulet structures, feature of the Owyhee project in piers, anchors, etc., and the second eastern Oregon and carries the ( the furnishing and installing o f the waters of the North Canal across pipe. Three hundred and thirty the valley of the Malheur River j calendar days were allowed for corn- near Ontario to irrigate 17,000 pletion. Twelve bids were received acres of bench lands on the Dead on November 26. 1934. The lowest combination was on the steel pipe Ox Flat division. The structure consists mainly of design, as follows: arc- welded plate-steel pipe, 80 Parker-Schram Co., Portland, Ore. inches in diameter, with compara Schedule No. 1 $64,764.50 tively short lengths of monolithic reinforced concrete pipe on the Consolidated Steel Corporation, Lor, Angeles, Calif.: ends. The f maximum head on the pipe is 268 feet and the total length I Schedule No. 2 ........... $522,457.00 Total ...................... $587,221.50 is 23,178 feet, or nearly 4tfe miles, making it one of the longest siphons The lowest bid on precast concrete of its size and type in the country. I pipe was submitted by the American The carrying capacity of the siphon I & stee, plpe C q Qf ^ is 325 cubic ieet per second. $501334 for the pipe the ends of the siphon was poured position while the fitters completed The pipe line crosses the John schedule, or about $40,000 more than in the warm weather of May and j entering the joint as the pipe came Day Highway, the Burns branch o f ! steel. The concrete type of con- June and in lengths of 48 feet. Cur- ! down. ing was done with Hunt process | Rocker arms were set at correct the Oregon Short Line Railroad, a structlon was also questioned on market road, three or four sm all, account of the low, flat. wet. heavily coating. Unseasonable cold weather location and the pin bearings grout- the plers at night after canals, and the channel of the Mai- aikalled land traversed by 1 mile in October found some of this pipe e(1 fast heur River It is encased in concrete o f the siphon line. Award was made not yet covered and round-about m e temperature of the pipe was intervals of uniform on all sides so that the pipe and buried in the ground under the | to the Parker-Schram Co. and the cracks developed at highways and railroad and is sup- consolidated Steel Corporation on about 10 to 15 feet. would occupy its normal position The alinement, grade and spacing with a minimum of internal stresses. p-ited across the river channel on December 28, 1934. The Parker- high concrete piers. Except for th e , Schram Co. sublet their excavation of the piers was very successfully During hot weather a length of undercrossings, and for several de- work to J. A. Terteling & Sons and managed, the supporting rings on pipe laying in the sun would be pressons in the ground profile, the the concrete to John Klug. The the steel pipe almost centering the noticeably longer on the sunny side pipe is supported about 15 inches Consolidated Steel Corporation sub- piers throughout. and, if placed with the free end on above the ground surface on con- let the field erection of the pipe to F A B R IC IA T IO N OF STEEL PIPE true center line, would shift position Crete piers, spaced, on the average. the Olson Manufacturing Co., of The pipe was fabricated in the when the temperature of the sides 60 feet apart, with the anchors plac Boise, Idaho. shops of the Consolidated Steel Cor became uniform if the end remained ed at about 1,000-foot intervals and There was much discussion among poration at Los Angeles. Alternate free. at each major bend in the pipe line. the bidders as to whether steel pipe length of about 36 t® 24 feet were In the erection of the pipe, all Pin bearings grouted into the top of should be fabricated at the home made up, the short lengtlis being of field joints were arc-welded in and each concrete pier carry rocker arms shops and shipped made up or heavier plate carrying stiffener j outside. Covered welding rod (Lln- freight should be kept which in turn support brackets at whether rings, which consist of two plates coin Fleetwood) was used through plates flat tached to stiffener rings which are down by shipping the 4 inches high by seven-six-teenths out. A fter a long series of try-outs welded to the shell of the pipe. The and fabricating in a temporary shop inch thick, 8 inches apart. Belland rocker arms are usually 18 inches in set up on the project. The lowest and spigot-type joints were used. All length but vary at depression in the bid was based on the fact that the shop welds were stress-relieved in an between the ground surface up to a maximum Union Pacific Lines annealing furnace All pipe lengths of 24 feet. The shell of the pipe shop at Los Angeles and the project were subjected to a hyrdostatic test offered clearance enough to allow varies from one-quarter to nine- in the contractor's shop, which in fabricated pipe two sixteenths inch in thickness and is loading of cluded a hammer test, the test high on cars. And so the pipe was self-supporting for the 60-foot pressure used being about 40 per ___ __ _ spans between piers. A design stress shipped, more than 400 carloads of cent above the working pressure. HELLO FRIEND S: Perhaps it of 14.000 pounds per square inch it, on racks 14 feet high from the Pipe was given an inside coat of bit- ! would be, Just 88 wel1 not to count was used in the pipe shell with an deck of the cars. umous primer and an outside coat ^'our cb'r ^i ns untd they have re- " turned ' from scratching ’ ’ ’ up your efficiency of 90 per cent in the PIERS AND ANCHORS of red lead before shipment. neighbor’s garden. sliop-welded longitudinal joint. Excavation for piers and anchors ERECTION OF PIPE -K N O T S — Expansion joints are provided was begun on March 10 and concrete On delivery at Ontario, pipe was Film star (using new toilet prep midway between the anchors. work followed within a week. All Twenty-six expansion joints, each o f Schedule No. 1, including the unloaded in an extensive yard by aration) This is awful stuff. Why In did you buy it? packed with five rings of 5-8 inch siphon inlet and outlet and anchors means of a caterpillar crane. this yard it was made up into 60- Maid—I read an advertisement in square lubricated flax packing, al was completed in July. foot lengths and some inside paint which you praised it very highly. low for a change in length of the Some difficulty was experienced ing was done before hauling on pipe line between anchors due to in securing suitable foundation for —K N O TS— contraction and expansion caused the piers across some of the low wet a truck and trailer to the location T O BUILDERS: We have every of the siphon. The first pipe was by temperature changes. Sixty-one bottom lands. A drain was dug par thing from cellar to roof for your manholes, spaced to about 350-feet allel to the siphon to keep the received on May 19 and placed in new house. Let us figure your plans intervals allow excess to the inside ground water below the surface and the highway undercrossing on May before you buy Building Material. Pipelaying was completed in o f the pipe. Six-inch air valves for several of the piers were overexca 22. —K N O TS— vacuum relief are provided at abrupt vated 8 to 12 feet in depth to reach October 1935. Guo wants to know if its' proof of An erection crew of eight men bends in the pipe and a 4-inch air shale, the overexcavation being evolution when a fellow turns turtle with a caterpillar crane could easily pressure and vacuum relief valve backfilled with coarse gravel. after he’s been drinking like a fish! was placed at the downstream end The monolithic concrete pipe at place 200 to 300 linear feet of pipe —K N O T S— per 8-hour shift. The program of Man—“ I want to get a present erection was to place first a length of pipe on an anchor pier and grout for my wife.” Nice Clerk—"Would you like to see the anchor. After allowing 3 or 4 days for the grout to set, the pipe something nice In silk things?” Man—"W hy er-r yes. But let’s was then erected from each anchor toward the expansion joints and tend to the present first.” —K N O T S — final connection was accomplished Don’t let the summer slip away by telescoping the expansion closed as far as possible, which allowed the before you get at that repair job. last length o f pipe to be placed in j Time flies, and before you know it, the opening freely, after which the winter will be here. Now is a good connection was made by pull-jacks time to re-roof, welded to the pipe. I - The lengths of pipe were swung into place by the crane with the pipe hanging about 30 degrees from the horizontal. The top of the circle at the low end of the pipe was then entered into the end of the line and Nyssa, Oregon tacked by a welder. The pipe was then lowered slowly to a horizontal | W e are now contracting our F A L L LETTUCE j A n g e !e s a t | in an effort to qualify local men, or at least Oregon residents as welders, it was finally admitted that field welding of pressure pipe is a special ized and difficult job in which not many are experienced and a great many could never become adapt. Qualified men were then employed wherever they could be found. For the first two months, progress was constantly retarded on account of lack of welders. After this time, pro gress was rapid and well balanced. Welding inside the pipe during the hot summer days was punishment to the welder and night-shift assign ments were in demand. As the pipe shell varied in thickness, from two to three beads or passes by the welder were required on the inside and the outside of each girth joint, two being sufficient for the one- fourth inch and three for any great er thickness. The average good welder could make six beads around the 80-inch pipe in a shift and make a joint that would not leak. Each bead was thoroughly peened with an air hammer before the next one was applied. Joints were tested for watertight ness by forcing soap suds under 50 pounds of pressure into the space between the spigot and the bell after the Inside and outside girth welds were completed. Very few joints showed any leakage. The bells were entered into the spigots 1H inches and the joints fitted so tightly that much difficulty was ex perienced in getting the suds to cir culate around the Joint. The Malheur siphon has not yet been filled with water, but the Owy hee siphon, constructed similarly in 1934 with the same inspector and several of the same welders and under a head of 350 feet, did not show a damp spot on the outside of a field weld when filled with water. Specifications provide for an inside shop coat of primer and a second coat of primer in the field followed by a hot coat of bituminous enamel not less than one-sixteenth inch in thickness. The outside shop coat of red lead is covered In the field by a final coat of aluminum paste in varnish. The bituminous primer and the aluminum were sprayed on with air brushes and the enamel applied hot with hand daubers. Thickness of the enamel coating and the pres ence o f pin holes or "holidays" were checked by a spark tester adjusted to spark through any coating of less than the specified thickness. It was first attempted to apply the enamel coating Inside the pipe in the yard where the pipe could be rolled and all painting done down- hand. This method requires much less material and nukes a smoother Nyssa by her youngest daughter, job because there is not splash and June. waste from overhead work. However, On a trip to Salt Lake City last hot sunshine on the outside red lead week, Mrs Chase says there were coat caused the enamel to sag and heat prostrations by the score, over run. Experiments showed that an 300 being reported in Salt Lake City aluminum outside coat would pro alone. T raffic officers were stationed test the enamel up to 95 degrees F. along the road to advise motorists and gloss white would protect up to to carry an Ice pack with them 110 degrees F. The latter was then through some of the hottest used until a cool day in August stretches of the road. showed that the enamel would crack from handling at 45 degrees F. Painting in the yard was then aban , Max Long who spent last week doned and the pipe was painted helping his grandfather. J. T. Long, after erection until a sharp cold with his farm work Is spending this snap around zero weather in late October showed that the enamel week with his other grandparents, would crack and loosen from the Mr. and Mrs. Charles Bullard. pipe in extremely cold weather. Painting was then stopped for the winter. Aluminum in rather thick varnish covered 325 square feet per gallon. The bituminous primer covered 400 square feet per gallon. The enamel required was 0.74 pound per square foot for painting in the yard as compared with 1.15 pounds per square foot for painting after erection. Old and new settlers on the Dead Ox Flat are beiginning to prepare for irrigation and it is planned to put the mlles-long siphon Into ser vice to carry water for fall seeding this year. CHASES TO LEAVE ON EASTERN TRIP Mrs. Florence Cha.ce and daughter Cherl expect to leave tomorrow by auto on an extended business trip to the east. En route they will stop for a few days at Denver, Kansas City, Columbus. Washington. D. C., and New York City. Miss Cheri ex pects to stay In the east and Mrs. Chase will be accompanied back to •»IHIilllllHIIIIIllllllllmiim'MIjiiimiimr S W A N BREAD makes golden brown slices of crispy toast for breakfast, for savory toasted sand wiches, or for that lunch at bedtime. The slices cut the ideal size for toasting. Watch the smile that goes round the table when you serve hot toast at any meal. PHONE 20 S W A N B AK E R Y NYSSA, OREGON Attractive low prices,..R O M A EIGH T-FORTY B R A N D Y JiPt. Pt. 5th 35 4 65 / $ 1.10 Buttled by America's greatest winery— ROMA WINE CO, Inc. Lodi, California ENJOY, TOO V E R M O U T H , . 9 0 f a bottle 2 type* — French & Italian A ZESTFUL A F FET I ZI I — S I I V I ROMA VEEMOUTH OFTEN ROMA Knot Hole News IGROWERS! Fall Lettuce than August 7th. See Us For • DEPENDABLE, LOW PRICED Our fieldman will contact you and those interested call or Tom F.ldridge Nyssa Phone 45 F.H. HOGUE NYSSA. O RE GON OFFICE PHONE 17 Spent in the Past 12 Months Jackson Lumber Company acreage. This must be planted not later • More Than *1,000,000 Hay Insurance You can’t afford to take the risk of having your hay burn and lose hundreds of dollars. Let us take the risk. Don’t delay another day, see . . . Denney R. Hogue Nyssa Phone 48 Nyssa Insurance Agency DON M. GRAHAM. Manager by Idaho Power with Local Business Firms ' I ' HE many different kinds of supplies, Our expenditures helped stimulate local materials and services required by our business, increase employment and pay rolls, business are purchased whenever possible build and maintain local business. within the territory we serve. Add to them the past year’s expenditure of our em- In the last 12 months alone, we paid to p'oyees— wages and salaries of $1,182,000.00 local firms and individuals more than $1,000,- —and our 1935 tax bUI 000.00. This huge sum of money was spent you for supplies, materials and services ranging part of the communities In which we live. in size and variety from the purchase of • of $020.000.90—and a picture of how much we are a This is only a part of Idaho Power's con bos of rubber bands to a carload of lumber. i d a h o get tribution to the territory we serve. V p o w e r €£ecPuciÛj..üot\ So MUCH-Co«t» So LITTLE!