PUBLIC NOTICE
INVITATION TO BID
MORROW COUNTY
NORTH END TRANS-
FER STATION
SCALE PIT FOUNDA-
TION PROJECT
MORROW
COUNTY
PUBLIC WORKS DE-
PARTMENT
MORROW
COUNTY,
OREGON
May, 2018
Sealed Bids for the “MOR-
ROW COUNTY NORTH
END TRANSFER STA-
TION SCALE PIT
FOUNDATION
PROJ-
ECT” will be received by
the Morrow County Pub-
lic Works Department,
365 West Highway 74
(P.O. Box 428), Lexing-
ton, Oregon, 97839, until
3:00 p.m. local time on
Thursday, May 24, 2018.
The bids will be publicly
opened and read at the
Morrow County Public
Works Department, 365
West Highway 74, Lexing-
ton, Oregon, at 4:00 p.m.
local time on Thursday,
May 24, 2018. First Tier
Subcontractor Disclosure
Forms will be accepted un-
til 5:00 p.m. on date of the
bid opening.
The County may reject
any bid not in compliance
with all prescribed public
bidding procedures and
requirements, and may
reject for good cause any
or all bids upon a finding
of the County that it is in
the public interest to do so.
The bidder must be regis-
tered with the Construction
Contractors Board.
The work will consist
of constructing concrete
base and walls as shown
in the Project Plans titled
“NORTH END TRANS-
FER STATION SCALE
PIT FOUNDATION”. The
contractor will construct
the form work and provide,
haul and place concrete re-
inforcing steel and struc-
tural concrete according
to the Project Plans. Mor-
row County Public Works
Department will perform
all site preparation, exca-
vations and backfill as re-
quired.
The work will consist of,
but may not be limited to,
the following total estimat-
ed unit cost quantities:
Mobilization,
Lump
Sum,1; Steel Reinforcing
for Concrete, 1920 Lbs;
Concrete (3300 psi), 31
Cu. Yds;
This is a MORROW
COUNTY Project by
and through THE MOR-
ROW COUNTY PUBLIC
WORKS DEPARTMENT,
fully funded by Morrow
County and is subject to
the current Oregon Bureau
of Labor and Industries
(BOLI) Prevailing Wage
Rates.
A Bid Bond in the amount
of 10% of the bid amount is
required with the proposal.
Performance and Payment
Bonds in the amount of the
contract bid amount will
be required of the success-
ful bidder.
The contractor will not be
required to have an asbes-
tos abatement license un-
der ORS 468A.720.
Plans and Bidding Docu-
ments may be obtained
at online at http://www.
co.morrow.or.us/rfps
or
by contacting the Mor-
row County Public Works
Department at (541) 989-
9500.
For additional informa-
tion, questions or con-
cerns, contact Sandi Point-
er by e-mail at spointer@
co.morrow.or.us or by
phone at (541) 989-9500.
MORROW COUNTY is
an equal opportunity em-
ployer.
Matt Scrivner
Morrow County Public
Works Director.
Published: May 2, 9, 16,
and 23, 2018
To discuss the budget for
the fiscal year July 1, 2018
to June 30, 2019 will be
held at 430 Hwy 207 Hep-
pner, OR 97836. The
meeting will take place
on May 15, 2018 at 5:30
PM. The purpose of the
meeting is to receive the
budget message and to re-
ceive comment from the
public on the budget. This
is a public meeting where
deliberation of the Budget
Committee will take place.
Any person may appear at
the meeting and discuss the
proposed programs with
the Budget Committee.
A copy of the budget docu-
ment may be inspected or
obtained on or after May
15, 2018 at 61232 Hwy
207 between the hours of
5:30 PM and 8 PM.
Published: May 2 and 9,
2018
Affidavit
PUBLIC NOTICE
MORROW
COUNTY
LAND USE HEARING
THE MORROW COUN-
TY BOARD OF COM-
MISSIONERS will hold
the following hearing of
public interest on Wednes-
day, May 30, 2018, at 9:00
a.m. at the Bartholomew
Building, Heppner, Or-
egon. Comprehensive Plan
Amendment AC-121-18:
OneEnergy Incorporated,
applicant, and Bill and
Rena Marquardt LLC,
owner. The property is de-
scribed as tax lot 3401 of
Assessor's Map 1N 25E.
The property is zoned EFU
and located north of Lex-
ington on Baseline Lane
between Lloyd Road and
Juniper Canyon Road. Re-
quest is to amend the Mor-
row County Comprehen-
sive Plan (MCCP) taking
an exception to Goal 3 Ag-
ricultural Lands to allow
for solar development on
up to 99 acres in the EFU
zone. Associated with this
request is Conditional Use
Permit CUP-N-331 which
was approved by the Plan-
ning Commission at a pub-
lic hearing on April 24,
2018. This Comprehensive
Plan Amendment is being
forwarded to the Board of
Commissioner’s with a ‘do
adopt’ recommendation.
Criteria for approval are
found in the MCCP Re-
view and Revision Process
which incorporates the cri-
teria found in the Morrow
County Zoning Ordinance
Article 8 Amendments.
This is the second of at
least two public hearings
with the final hearing be-
fore the Board of Commis-
sioners.
Opportunity to voice sup-
port or opposition to the
above proposal or to ask
PUBLIC NOTICE
NOTICE OF BUDGET
COMMITTEE MEETING
IONE SCHOOL DIS-
TRICT #2
NOTICE IS HEREBY
GIVEN, pursuant to ORS
294.426, that a meeting of
the budget committee of
the Ione School District #2
will be held on the 22nd
day of May, 2018 at 5:30
p.m. for the purpose of
receiving the budget mes-
sage and budget document
of the district for the fiscal
year 2018-2019. The meet-
ing will be held at the Ione
Schools, 445 Spring Street,
Ione, Oregon.
This is a public meeting
where deliberations of the
budget committee will take
place and any person may
appear and comment on
proposed programs with
the budget committee at
that time. A copy of the
budget document will be
available at Ione Schools
at the time of the meeting.
Jon Peterson, Superinten-
dent & Budget Officer
April 25, 2018 and May 9,
2018
Web Page May 1-22, 2018
http://www.ione.k12.or.us
Published: April 25 and
May 9, 2018
Affidavit
PUBLIC NOTICE
Notice of Budget Commit-
tee Meeting
A public meeting of the
Budget Committee of the
Heppner Cemetery Main-
tenance District, Morrow
County, State of Oregon.
Heppner Gazette-Times, Heppner, Oregon Wednesday, May 9, 2018 -- SEVEN
questions will be provided. Plan to add a locally sig- cient specificity to afford
Failure to raise an issue nificant aggregate site to the decision maker an op-
in person or by letter or the Morrow County Com- portunity to respond to
failure to provide suffi- prehensive Plan (MCCP) the issue precludes appeal
cient specificity to afford Inventory of Natural Re- to the Land Use Board of
the decision maker an op- sources - Aggregate and Appeals based on those is-
portunity to respond to Mineral Resources. Cri- sues.
the issue precludes appeal teria for approval for Copies of the staff report
to the Land Use Board of CUP-N-329 includes the and all relevant documents
Appeals based on those is- Morrow County Zoning will be available after May
sues.
Ordinance (MCZO) Ar- 18, 2018.
Copies of the staff reports ticle 3 Section 3.010 EFU For more information,
and all relevant documents and Article 6 Conditional please contact Stephanie
will be available after May Uses. This is the third of Loving at 541-922-4624 or
18, 2018. For more in- at least three hearings with 541-676-9061, extension
formation, please contact the final decision issued by 5506.
Carla McLane at 541-922- the Planning Commission. DATED this 9th day of
4624 or 541-676-9061, ex- Criteria for approval for May 2018.
tension 5505.
AC-117-18 is found in the MORROW
COUNTY
DATED this 9th day of MCCP Natural Resources PLANNING
DEPART-
May 2018.
Element and Review and MENT
MORROW
COUNTY Revision Process which Published: May 9, 2018
PLANNING
DEPART- incorporates the criteria Affidavit
MENT
found in the MCZO Article
Published: May 9, 2018
8 Amendments. This is the
Affidavit
third of at least four pub-
lic hearings for AC-117-18
with the final hearing be-
PUBLIC NOTICE fore the Board of Commis-
MORROW
COUNTY sioners.
Continued from April 24,
LAND USE HEARING
THE MORROW COUN- 2018: Comprehensive Plan
TY PLANNING COM- Amendment AC-120-18:
MISSION will hold the Morrow County, propo-
following hearings of pub- nent. Request is to adopt
lic interest on Tuesday, a Parks Master Plan as a
May 29, 2018 at 7:00 p.m. resource document in sup-
at the Port of Morrow Riv- port of Goal 8 Recreation
erfront Center, Boardman, of the Comprehensive
Plan. The Parks Master
Oregon.
Continued from April 24, Plan is applicable to Mor-
2018: Conditional Use Per- row County Parks – An-
mit CUP-N-329 and Com- son Wright, Cutsforth and
prehensive Plan Amend- OHV. The criteria for ap-
ment AC-117-18: Aaron proval are found in MCCP
Heideman, applicant and Review and Revision Pro-
The Heppner
owner. The property is cess. This is the third of at
described as tax lots 2801 least four public hearings
Gazette Times
and 2807 of Assessor's with the final hearing be-
Map 1N 26. The property fore the Board of Commis- 188 W. Willow
is zoned Exclusive Farm sioners.
Heppner, OR
Use (EFU) and located off Opportunity to voice sup-
97836
Kemp Lane northeast of port or opposition to the
Lexington. Request is to above proposal or to ask
allow by conditional use questions will be provided. (541) 676-8229
mining and processing of Failure to raise an issue
david@
aggregate resources and in person or by letter or
rapidserve.net
amend the Comprehensive failure to provide suffi-
Business
Card
Printing
PUBLIC NOTICE
Published: May 9 and 16, 2018
Affidavit
PUBLIC NOTICE
PUBLIC NOTICE
NOTICE OF BUDGET HEARING
A meeting of the Morrow County Health District Board of Directors will be held on May 21, 2017, 7:00 pm, at
the Pioneer Memorial Clinic Conference Room, Heppner, Oregon. The purpose of this meeting is to discuss
the budget for the fiscal year beginning July 1, 2017, as proposed by the Morrow County Health District Board.
A summary of the budget is presented below. A copy of the budget may be inspected or obtained at MCHD
Administration Office, 564 E. Pioneer Dr, Heppner, Oregon, between the hours of 8:00 am and 5:00 pm or by
calling 541-676-2925. This budget was prepared on a basis of accounting that is consistent with the preceding
year. This budget is for an annual period and has only one fund.
Financial Summary
Anticipated Requirements
Adopted Budget
This Year 2017-2018
Proposed Budget
Next Year 2018-2019
1.
2.
3.
4.
5.
6.
7.
Total Personal Services
Total Materials and Supplies
Total Capital Outlay
Total Debt Service
Total Contingencies
Total All Other Expenditures and Requirements
Unappropriated Amount Reserved for Future Use
$
8,916,557
3,330,844
1,307,240
258,061
-
1,172,035
65,618
$
9,892,203
3,628,159
1,196,625
283,848
-
612,959
300,380
8.
Total Requirements - add lines 1 - 7
$
15,050,355
$
15,914,174
9. Total Resources Except Property Taxes
10. Total Property Taxes Estimated To Be Received
11. Amount Used From Prior Year Cash Reserve
$
13,553,964
1,496,391
-
$
14,016,625
1,897,549
-
12. Total Resources - add lines 9 - 11
$
15,050,355
$
15,914,174
Published: May 2 and 9, 2018
Affidavit
NOW YOU CAN SEARCH OLD
COPIES OF THE HEPPNER
GAZETTE-TIMES ON-LINE:
1883-1976
Anticipated Resources
Estimated Ad Valorem Property Taxes
13. Total Property Taxes Estimated To Be Received
14. Plus: Estimated Property Taxes Not to be Received
A. Loss Due to Constitutional Limits
B. Discounts Allowed, Other Uncollected Amounts
$
15. Total Tax Levied - add lines 13, 14A & 14B
$
Tax Levies By Type
16. Permanent Rate Limit Levy ($/1,000)
17. Local Option Taxes ($/1,000)
18. Levy for Bonded Debt or Obligations
Published: May 9, 2018
Affidavit
1,496,391
$
1,897,549
240,280
53,712
1,790,383
260,000
66,728
$
2,224,277
Rate or Amount
Rate or Amount
.6050
.3900
0
.6050
.3900
0
G T
azette
imes
http://oregonnews.uoregon.edu
P.O. Box 188 W. Willow Street, Heppner Telephone: (541) 676-9228 Fax: (541) 676-9211.
E-MAIL: PUBLISHER: david@rapidserve.net
EDITOR: editor@rapidserve.net
ADVERTIZING: megan@rapidserve.net
BOOKKEEPING: april@rapidserve.net
The Official Newspaper of the City of Heppner and the County of Morrow