November 18, 2016 | Cannon Beach Gazette | cannonbeachgazette.com • 3A Nehalem River replacement bridge serves as model New bridge is designed to withstand major seismic event By Dave Fisher For EO Media Group NEHALEM — Building a bridge to withstand “the big one,” a Cascadia Subduction Zone earthquake, has been ev- er-present on the mind of Til- lamook County Public Works director Liane Welch ever since a winter storm in 2007. The replacement of the 382-foot Lommen Bridge, which spans the main stem of the Nehalem River on Miami-Foley Road, became Welch’s number one priority. In December of that year, the north Tillamook County bridge, which dates back to 1955 and is named after a pi- oneer family, shifted as much as 3 inches on its foundation when debris carried by the riv- er stacked up against the base of the structure. The bridge, according to Welch, had the dubious honor of being rat- ed the second worst bridge in terms of safety in Oregon, second only to Portland’s Sellwood Bridge, which has since been replaced. The 12.5-mile Miami-Fo- ley Road east of U.S. High- way 101 serves as a detour route linking north Tillamook County to its neighbors to the south in the event the main coastal highway is closed. “If the bridge were to fail, we no longer have this vital line during an emergency; the Miami-Foley is the backbone of the north county transpor- tation system,” said Welch in explaining why it was import- ant to design a structure that would not only hold up during a winter flood but also to a major seismic event. To that end, the bridge incorporates the use of isolation bearings atop foundations, which act as shock absorbers of sorts to minimize damage during large earthquakes. With the recent completed fabrication and installation of the rigid steel framework the bridge is beginning to look more like a bridge. Tradi- tionally, concrete is used in almost 80 percent of bridge construction, however that could change in the future, according to Steve Fugate, president of Northwest-based Fought and Co., steel fabri- cator for the Nehalem River bridge project. “Since we can construct longer spans with faster in- stallation, we’ve shown that steel is a great environmental choice, especially with bridg- es spanning rivers and water- ways,” said Fugate. Building bridges over wa- ter adds to the complexity by strictly limiting work in the water and providing a short window of time allowed for each season. Using steel has provided the opportunity to save time in the construction schedule. “We are striving to reduce the number of 24-hour shifts during the water season for less impact on the public and the environment,” added Scott Butler, project manag- er for the bridge contractor, Farline Bridge. After a “pretty rough win- ter” this past year with rising river waters the project is still on schedule, says Welch of the nearly $11 million project, made possible with a $10 mil- lion grant, 90 percent of which is federally funded with a 10 percent local match. Barring any weather-related delays, the project will be completed in the fall of 2017. One thing that won’t change is the name; the new bridge will still be called Lommen Bridge. During construction, Welch reminds motorists to be aware that the traffic pattern has changed slightly in the vi- cinity of milepost 11.5 where construction is taking place. There will be two lanes open DAVE FISHER/FOR EO MEDIA GROUP With the steel framework now in place the new Lommen Bridge, which spans the Nehalem River on Miami-Foley Road in north Tillamook County, is beginning to take shape. ‘If the bridge were to fail, we no longer have this vital line during an emergency.’ Liane Welch, Tillamook County Public Works director unless the flaggers are needed at certain times. “Also, the speed limit through the work zone is post- ed as 30 miles per hour and the sheriff has been enforcing this area more frequently, so please drive safely.” Coastal Advantage 503.436.1777 • Coastal Advantage.com DAVE FISHER/FOR EO MEDIA GROUP Isolation bearings, say bridge designers, will minimize damage to the bridge during large earthquakes. Alaina Giguiere Marty Giguiere Owner/Principal Broker c: 503.440.3202 f: 877.812.1126 e: alainagiguiere@mac.com Owner/Broker c: 503.440.7676 o: 503.43t6.1777 e: mr007@pacifi er.com Susan Tone Maryann Sinkler Andrea Mace Broker c: 503.354.4072 e: suanetone@nehalemtel.net Broker c. 503.440.9280 e: maryanns@remax.net Broker c. 503-440-4024 e: Andrea.k.mace@remax.net Egrane Brown Broker c: 503.440.1648 e: egranebrown@gmail.com /REMAXCoastalAdvantage “Our Featured Properties” • Please visit our website to view all our properties! 1868 PACIFIC ST. 2030 N. OCEAN AVE. 3436 SUNSET BLVD 187 MADISON 8730 BRAERIDGE SALE PENDING SALE PENDING NEW LISTING Gearhart • $1,988,000 Seaside • $1,595,000 Cannon Beach • $1,450,000 Manzanita • $1,075,000 159 NEBESNA ST 151 E NELCHENA CT 79364 RAY BROWN RD OCEAN VIEW - 1832 HAYSTACK LN OCEAN VIEW - 196 E SUSITNA Cannon Beach • $899,000 Cannon Beach • $799,900 Falcon Cove • $850,000 Cannon Beach • $799,000 Cannon Beach • $720,000 4488 S HEMLOCK 1631 S. SPRUCE 352 SUNSET BLVD 2787 S HEMLOCK 576 6TH STREET LI NE ST W IN G Cannon Beach • $3,350,000 NEW LISTING Cannon Beach • $599,000 Cannon Beach • $539,000 Cannon Beach • $529,000 512 BREAKERS POINT 4241 S HEMLOCK OCEAN-FRONT CONDO - TOLOVANA INN Cannon Beach • $499,000 Cannon Beach • $479,000 MEET OUR NEWEST AGENT Cannon Beach • $459,000 Cannon Beach • $439,000 1320 CASCARA LN C-5 SANDCASTLE CONDOS SALE PENDING Cannon Beach • $335,000 Cannon Beach • $339,000 SCAN HERE to go to our website Cannon Beach • $229,000 Geri Lane • Broker NOW WITH 2 LOCATIONS TO SERVE YOU! 219 N. Hemlock in Downtown Cannon Beach 503.436.1777 430 Laneda in Downtown Manzanita 503.368.1777 www.CoastalAdvantage.com c. 503-480-9846 gerilane@remax.net We are pleased to have her as part of our team! Member of 2 MLS Systems Each offi ce is independently owned & operated “Real Estate standards for those with ‘Higher’ Expectations. above the crowd!”