K-8 Academy
construction
The Warm Springs K-8 Academy is on sched­
ule for completion in four months: The comple­
tion date is estimated at July 18.
One area o f the 80,000-squarè-foot school—
the classrooms for the kindergarten through sec­
ond grades— are already painted on the inside.
Meanwhile, construction workers are preparing
the water line that will serve the school. A new
water tower will be constructed near the existing
one, and the line will follow Chukar and then cut
across a lot to the school. A good view o f the
school is from the main bus entrance area, off
Tenino.
The weather has been good lately, allowing for
the w ork to continue at a good pace. Kirby
Nagelhout Construction Co. o f Bend is thè gen­
eral contractor on the $20 million project.
Heavy machinery
operator (above)
Owen Danzuka
works on the water
line crossing at
Chukar Street. Fred
Jack (right) works
on the painting of
the k-2 wing. At
lower left is the
gymnasium.
Dave McMechan photos.
-