Vernonia's voice. (Vernonia, OR) 2007-current, January 24, 2012, Page 3, Image 3

Below is the OCR text representation for this newspapers page. It is also available as plain text as well as XML.

    in other words
january24
2012
What it Takes to Build A School – Part I
By Dr. Ken Cox
Superintendent Vernonia School Dis-
trict
 
When it all started it all seemed 
so  simple;  we  were  going  to  build  a 
school. What I have learned since those 
naïve days is that this is a far more com-
plex endeavor than I ever imagined. 
 
As  I  think  back  I  can  see  that 
there  has  been  three  distinct  phases  to 
the project: determining the best site, the 
whole  FEMA-NEPA  process  of  identi-
fying and then meeting federal program 
guidelines, and then finally construction. 
However,  the  construction  has  many 
parts  as  well:  the  wetlands  on  the  site, 
the  utility  and  street  changes  on  both 
Missouri Ave and Bridge St, the building 
construction itself, the future demolition 
of  our  existing  schools,  and  finally  the 
construction of the replacement Spencer 
Park. 
 
What I would like to do is give 
you  a  breakdown  of  each  of  the  differ-
ent projects and how we are progressing 
on  them.  In  this  article  I  will  touch  on 
what  has  been  done  and  in  process.  In 
Part II I will talk about what is to come: 
the demolition, park construction, future 
community involvement, and the overall 
budget.
Wetlands Mitigation
 
When we first identified the site, 
the  first  order  of  business  was  to  pur-
chase  enough  land  to  go  with  Spencer 
Park to build a school. We ended up pur-
chasing five pieces of property from four 
different owners. Once the property was 
secured  the  biggest  challenge  was  the 
nearly four acres of wetlands. By law we 
must mitigate, or replace, these wetlands 
with  twice  as  much  comparable  wet-
lands.  We  looked  at  two  different  sites 
for these mitigated wetlands: one in Ver-
nonia and the other a stream restoration 
along a nearby creek. After many discus-
sions we determined that it would be best 
to go with the wetlands in Vernonia and 
we worked with the City of Vernonia to 
create the wetlands that are now fenced 
in  orange  about  a  quarter  mile  west  of 
Vernonia  Lake.  This  seven  acre  parcel 
has been designed and created so that it 
will  collect  water  and  maintain  enough 
moisture  to  maintain  native  plant  spe-
cies.  In  fact,  the  site  will  be  monitored 
for the next five years to make sure that 
the  plants  have  survived  under  typical 
weather conditions. 
 
As we began the wetlands con-
struction  we  have  continually  looked 
for  ways  to  provide  for  collaboration 
between the different aspects of the en-
tire  project  and  the  community.  Some 
examples  of  this  are  our  forestry  class 
which will assist the landscaper in some 
of the planting in the spring, both at the 
new school  site  and at the  wetlands. In 
addition, we will work with the City to 
amend  our  Intergovernmental  Agree-
ment  to  allow  our  students  to  maintain 
the wetlands rather than pay the City to 
do so. And another aspect of collabora-
tion  is that the wetlands will be used as 
a hands-on part of our natural resources 
curriculum,  as  we  will  eventually  have 
learning  stations  placed  around  the  en-
tire wetlands. The wetlands will also be 
included as an integral part of the City’s 
overall  park  design  for  all  of  the  prop-
erty between Vernonia Lake and the new 
Spencer  Park  (where  the  schools  are 
now).
 
Initially  we  budgeted  $300,000 
for the wetlands development. In June of 
2011, we decided to increase the budget 
to  $500,000  based  on  the  information 
we  had  at  the  time.  We  then  published 
a  Request  for  Proposals  (RFP)  and  out 
of  over  20  companies  who  showed  in-
terest  we  selected  the  lowest  bidder  at 
$875,000.  We  believe  the  increase  was 
due at least in part to the uncertainty on 
the number of concrete foundations that 
were  buried  in  the  underbrush  on  the 
site. We continue to work with the land-
scape  contractor  on  this  project  to  find 
ways to reduce this total cost. One way 
is  to  use  natural  plant  species  that  Mr. 
Project Budget by Category
CONSTRUCTION TOTAL
DESIGN/PERMITTING
PROJECT MANAGEMENT
ENVIRONMENTAL TESTING/
MITIGATION/PERMITTING
REAL PROPERTY
MISCELLANEOUS COSTS
FUNDRAISING/FINANCING COSTS
CONTINGENCY 
PROJECT TOTAL COST
$30,000,000
$4,200,000
$800,000
$1,600,000
$1,600,000
$300,000
$1,000,000
$500,000
$40,000,000
Miller can get from the Bureau of Land 
Management at no cost and the other is 
to have students help with the planting in 
the spring.
Off-Site Construction (Missouri  Ave. 
and Bridge St.)
 
I remember sitting in a meeting 
at  the  ODOT  Offices  in  Portland  when 
they told us that their initial estimate to 
widen Bridge Street at the new site was 
$6,000,000. I didn’t want to believe them 
especially  since  we  had  only  budgeted 
$3,300,000 for all the work necessary on 
both Missouri Avenue and Bridge Street. 
We  were  all  very  pleased  to  hear  Gov-
ernor  Kulongoski  at  the  groundbreak-
ing in December of 2010, announce that 
the  state  would  provide  $3,800,000  for 
the project. Because the ODOT funding 
could not be used for utilities,  we began 
a separate project to deal with the off-site 
utilities. We have worked with the Plan-
ning  Commission  and  WOEC  to  move 
the  electric  lines  from  underground  to 
overhead in order to save over $80,000 
on the project. At ODOT’s request, rath-
er than going straight down Missouri to 
Bridge  and  then  east  along  Bridge,  we 
had  the  sewer  lines  go  east  along Ala-
bama  (before  they  got  to  Bridge)  and 
then along the St. Mary’s property down 
the gulley to go under Bridge Street. We 
also published an RFP for the sewer and 
storm  water  run-off  from  the  site  south 
along  Missouri. This  work  has  met  nu-
merous  challenges:  the  first  was  there 
was solid rock in part of the excavation. 
Then  we  found  that  the  existing  sewer 
line beneath Bridge St. was not adequate 
to handle the new school’s needs and so 
we  are  having  to  bore  underneath  the 
highway to install a bigger line down to 
the pump station.
 
On the budget side, once ODOT 
became part of the project we no longer 
had  to  worry  about  the  street  improve-
ments. But, we still needed to deal with 
the  underground  utilities.  The  original 
bid award for the storm water/sewer RFP 
was $275,000, but due to issues, includ-
ing the extensive sewer line extension I 
described  above,  that  cost  is  currently 
estimated at $400,000.
Building Construction
 
When  we  began  looking  for  a 
contractor to build our schools we chose 
to  use  a  construction  model  known  as 
CMGC,  which  stands  for  Construction 
Manager General Contractor. The basic 
premise  of  this  construction  model  is 
that  we hire a  contractor early on,  who 
then works with the architects through-
continued on page 6
3
Publisher and Managing Editor
Scott Laird
503-367-0098
scott@vernoniasvoice.com
Contributors
Mackenzie Carr
Dr. Ken Cox
Chip Bubl
Nate Izzett
Bill Langmaid
DeAnna Pearl
Sonia Spackman
William Wells
Photography
Yaraslava Denysenko
Scott Laird
Jonah Ooten
Mystery Pentz
Want to advertise?
Have an article?
Contact: scott@vernoniasvoice.com
One year subscriptions
(24 issues) $35
Vernonia’s Voice is published
on the 2nd and 4th Tuesday
of each month.
Vernonia’s Voice, LLC
PO Box 55
Vernonia, OR 97064
503-367-0098
www.VernoniasVoice.com
STOP
THE DROP
The Vernonia Senior
Center womld like yomr
donations... BUT they
mmst be left dmring
bmsiness homrs ONLY
Mon-Fri 9:00 AM - 3:00 PM
Please DO NOT leave
items omtside
For after hours drop-off please
contact Pauline 503-429-5810
Happy Hour Mon-Fri 4-7
Lady’s Night Wed 5-12
“STILL BIKER FRIENDLY”
LIVE MUSIC
Sat, 1/28
Sat, 2/4
Sat, 2/11
Sat, 2/18
“Gretchen Mitchell” R & B
“Franco Paletta & the Stingers” Jammin’ Blues
“The Insensitives” Valentines Day Party
“Vegas Sun” Rock& Roll
Mon & Tues 10am-6pm, Cafe Closed • Wed 10am-6pm, Cafe 10am-5pm
Thr-Fri 10am-7pm, Cafe 10am-6pm • Sat 10am-11pm, Cafe 10am-10pm
Sunday 10am-2pm, Cafe 10am-2pm (or call)
11139 Highway 202
(503) 755-2722
• Specialty hamburgers
• Draft beer & mixed drinks
• Pool tables & satelite TV
• Special live music events
• Free Wi-fi
Sun - Thurs 11 AM - Midnight •
733 Bridge St, Vernonia
Jan. 28
Stepchild
Feb. 3 & 4
Play it Again
Karaoke
Feb. 18
Stepchild
Gift certificates available
Fri - Sat 11 AM - 2:30 AM
• 503-429-9999